Increase of 150 million cubic meters of Iran’s gas production capacity until 1406 – rahnam

According to rahnam news agency, “Mohammad Hossein Mutjali” stated that plans have been defined in the Pars Oil and Gas Mission in order to maintain the country’s gas production, and said: The first phase of the Kish gas field development plan is being implemented and so far four wells of this field It has been completed by Iran’s National Drilling Company and is ready for production.

Stating that the tender for the purchase of the pipeline of this gas field is underway, he said: Also, the issues related to the marine facilities company are obtaining the necessary permits.

The CEO of Pars Oil and Gas Company, referring to the Farzad B joint gas field development plan, said: Now the basic design studies for the development of this joint field are being carried out, and its contractor will be Petropars Company, and the jacket of this field will be built by Marine Facilities Company.

Motjali stated: The next field in increasing gas production is the North Pars gas field, the basic design studies for phase one are in the final stages, and we are conducting tenders for the construction of the jacket of this field, as well as for other sectors such as drilling and pipeline, packages The tender has been prepared and this tender will be concluded next year.

He pointed to the development plan of Bilal gas field and added: Various packages for the development of this field have been finalized and only the pipeline supply package remains, the tender of which will be held by Petropars as the main contractor of this phase.

The CEO of Pars Oil and Gas Company stated that four wells have been completed in Phase 11 of South Pars and on platform 11 B and gas production is underway. we start

Motjali continued: Various issues such as jacket installation are being done for platform 11 A, and drilling on this position is going through the tender process in Petropars. Platforms 11 A and B are under IPC contract and with Petropas investment.

He stated that with the implementation of the first step of the development projects in four gas fields, until the end of 1406, the country’s daily gas production will increase to more than five standard phases of South Pars, he clarified: the capacity of each phase of South Pars is 28 million cubic meters per day and with This account will add 150 million cubic meters per day to the country’s gas production capacity.

The CEO of Pars Oil and Gas Company, emphasizing that the increase in gas production from the first stage of the North Pars field development plan will be 28 million cubic meters per day, said: 28 million cubic meters of gas will be produced from the Farzad B joint field.

Motjali added: The production in the first phase of Kish gas field will be equivalent to the three phases of the South Pars standard, and 14 million cubic meters of gas will be produced daily in the first phase from Bilal field.

He continued: In total, with the full implementation of development projects in Pars Oil and Gas Company, the equivalent of 13 phases of the South Pars standard will be added to the country’s gas production.

The CEO of Pars Oil and Gas Company stated that the first row of Jask terminal is ready for operation and said: The part related to Pars Oil and Gas Company has made good progress and we will be ready to receive crude oil from the Gore-Jask crude oil pipeline.

end of message/